MATUGGA, Wakiso District — Dei BioPharma has pushed back against opposition allegations regarding the government’s Shs723 billion investment, stating that the transaction followed an independent assessment by the Chief Government Valuer.

Speaking at a press briefing at the company's manufacturing site in Matugga, Wakiso District, founder Dr Matthias Magoola called claims raised by the Leader of the Opposition "not true". He said a government team—including consultants from the Ministry of Finance, Planning and Economic Development and the Ministry of Works and Transport—conducted the valuation, and pledged that the company would table the report.

Valuation and Shareholding

Board chairperson Dr Patrick Wakida said the valuation placed the facility and its intellectual property at $2.1 billion, lower than directors' estimates of $2.6 billion to $2.8 billion. Pricing the state's entry on the lower figure, the government’s Shs723 billion bought a 9.4% stake.

"It was not Dei that valued the property," said Dr Wakida, who is also the Member of Parliament for Kabweri County. "The valuation was done by the Government Valuer."

Dr Wakida noted that he signed the investment agreement in the presence of the Attorney General, the Minister of Finance, and the Minister of Science, Technology and Innovation.

To counter claims that the state received nothing in return for the funds, Dei BioPharma displayed share certificates:

• One certificate is held by the Ministry of Finance, Planning and Economic Development.

• Another is held by the minister responsible for Science, Technology and Innovation.

• Both are registered with the Uganda Registration Services Bureau (URSB).

Project Costs, Financing, and Jobs

The briefing comes as Dei BioPharma seeks additional funding to finish its Matugga complex:

• Total project cost: Estimated at $1.1 billion.

• Funds raised prior to state investment: About $500 million from group businesses, commercial lenders, and private partners.

• Remaining funding needed: Approximately $430 million.

Dr Magoola described the state's contribution as bridge financing after funding for the next phase ran into obstacles, adding that the company plans to repay it as soon as possible. Officials said the government could increase its stake in future rounds, with the company open to selling up to roughly 30% of its shares and exploring a future stock market listing.

Dr Wakida defended the investment as standard state backing for local projects with broad economic impact. The facility currently employs around 500 people and could support up to 40,000 jobs once fully operational.